The HS2 high-speed rail project has an “unrealistic timetable” and faces major cost pressures, a report by the National Audit Office has said.
The £56bn programme has too ambitious a schedule and rising costs could mean that not all its intended benefits are delivered, the NAO said.
The NAO said the 2026 target opening date for the first phase was “at risk, despite good progress”.
But HS2 Ltd said it was confident that it could achieve its objectives.
The first phase of HS2, linking London and the West Midlands, is due to be completed in 10 years’ time.
Trending
- GEORGIA STATE ELECTION BOARD FACES SCRUTINY
- RUSSIA’S AIR DEFENCE DESTROYS 47 UKRAINE DRONES
- OFFICERS ARRESTED FOR INVOLVEMENT IN TRAFFICKING
- WATER FIRMS ORDERED TO PAY BACK CUSTOMERS £158M
- MAN CITY & PREMIER LEAGUE WELCOME PANEL RULING ON SPONSORSHIP DEALS
- UK ESTABLISHES REGULATORY INNOVATION OFFICE
- TORY LEADERSHIP CANDIDATES TO BE WHITTLED DOWN IN VOTE
- ‘WE HAVE TO WIN THIS ELECTION’ SAYS TRUMP