The HS2 high-speed rail project has an “unrealistic timetable” and faces major cost pressures, a report by the National Audit Office has said.
The £56bn programme has too ambitious a schedule and rising costs could mean that not all its intended benefits are delivered, the NAO said.
The NAO said the 2026 target opening date for the first phase was “at risk, despite good progress”.
But HS2 Ltd said it was confident that it could achieve its objectives.
The first phase of HS2, linking London and the West Midlands, is due to be completed in 10 years’ time.
Trending
- KANE LEADS THE BUNDESLIGA SCORERS’ LIST WITH 21 GOALS
- SLOT TAKES PRIDE IN HOW LIVERPOOL EXITED CHAMPIONS LEAGUE
- TRUMP’S STEEL AND ALUMINUM TARIFFS TAKE EFFECT
- EU TO IMPOSE COUNTER TARIFFS ON $26 BILLION IN US GOODS
- GERMANY PLANS TO TURN AWAY ASYLUM SEEKERS AT THE BORDER
- UKRAINE SAYS THEY ARE READY TO ACCEPT CEASEFIRE PROPOSAL AND NEGOTIATIONS
- PSG HOPING TO DEFY THE ODDS AT ANFIELD
- FOREIGN CRIMINALS COULD FACE E-TAGS AND CURFEWS BEFORE DEPORTATION